Stress risk assessment template, with a filled-in example for a small business

A stress risk assessment template can be a simple table with one row for each of HSE's six Management Standards areas – demands, control, support, relationships, role and change – recording what you found, who is affected, what you already do, what more you will do, who owns each action, by when, and how you will review it. Below is one such template, then a filled-in example for a fictional civil engineering contractor. The law prescribes no form: with five or more employees, you must record the significant findings, any group especially at risk and your arrangements for planning, organising, monitoring and reviewing the measures that follow. HSE also publishes a general template and three example stress assessments.

Updated 11 October 2026 · 11 min read

What the written record must hold

With five or more employees, the regulations ask for two written records. They apply in Great Britain; Northern Ireland's 2000 regulations word both the same.

MHSWR 1999 reg 3(6)Where the employer employs five or more employees, he shall record— (a) the significant findings of the assessment; and (b) any group of his employees identified by it as being especially at risk.MHSWR 1999 reg 5(2)Where the employer employs five or more employees, he shall record the arrangements referred to in paragraph (1) – those for the effective planning, organisation, control, monitoring and review of the preventive and protective measures.HSWA 1974 s.20(2)(k)An inspector may require the production of, inspect and take copies of the documents the law requires you to keep.MHSWR (NI) 2000 regs 3(6), 5(2)The same two records, in the same words, in Northern Ireland.

The regulations set no format and no length. HSE's guidance on stress puts it like this:

«Any paperwork you produce should help you communicate and manage the risks in your business. For most people this does not need to be a big exercise – just note the main points about the significant risks and what you decided.»
HSE, Stress risk assessment

The record is not a report to anyone. Nothing is filed with HSE: you keep it, and produce it if an inspector (HSE or your local authority; HSENI in Northern Ireland) asks. With fewer than five employees you need not write it down, though HSE notes a record is useful for reviewing later. The duty to assess applies whatever your size – see what the law requires.

The template: one row per HSE area

Start with a short header, then fill in one row for each of HSE's six areas. Copy both tables into a document or spreadsheet; a dash marks a field you fill in.

Organisation
What to writeName, what you do, number of employees, sites and teams
Date of assessment
What to writeWhen the assessment was agreed
Carried out by
What to writeWho led it, and the competent person who helped
Who was consulted
What to writeSafety representatives, if you have them, or employees directly – and how
Evidence used
What to writeAbsence and turnover figures, conversations, group discussions, a survey if you ran one
Groups especially at risk
What to writeAny team, site or role more exposed than the rest (MHSWR 1999 reg 3(6)(b))
Arrangements
What to writeWho owns the plan and how progress is checked and reviewed (reg 5(2)); how staff hear about it (reg 10)
Next review
What to writeA date, and what would bring it forward
Demands – workload, work patterns, the work environment
What we found, and who is affectedCan people cope with their workload in their agreed hours? Where are the peaks? Who: Teams, roles or seasons with the heaviest load.
What we already doHow work is planned, staffed and scheduled
What more we will do: owner, by when, review–
Control – how much say people have in their work
What we found, and who is affectedDo people have a say in how and at what pace they work? Who: Roles with little say.
What we already doHow staff help plan their own work
What more we will do: owner, by when, review–
Support – from the organisation, line managers and colleagues
What we found, and who is affectedDo people get the help, information and feedback they need, and know where to find it? Who: New starters, people working away from a base, teams with a new manager.
What we already doOne-to-ones, induction, who staff can talk to
What more we will do: owner, by when, review–
Relationships – positive working, unacceptable behaviour
What we found, and who is affectedIs there conflict or unacceptable behaviour? Can people report it, and does anything happen? Who: Teams where complaints or disputes cluster.
What we already doPolicy on unacceptable behaviour, how reports are handled
What more we will do: owner, by when, review–
Role – clear roles that do not conflict
What we found, and who is affectedDo people know what is expected of them? Do demands from different managers clash? Who: Roles that answer to more than one manager.
What we already doJob descriptions, who settles clashes
What more we will do: owner, by when, review–
Change – how change is managed and communicated
What we found, and who is affectedAre people told about changes in time, and consulted before they are decided? Who: Teams going through change now or soon.
What we already doHow changes are announced and discussed
What more we will do: owner, by when, review–

A filled-in example (invented): a civil engineering contractor

Date of assessment
Fictional contractor (invented)April 2026
Carried out by
Fictional contractor (invented)The managing director, with the office manager as competent person
Who was consulted
Fictional contractor (invented)The union safety representative at each stage; all staff at team briefings
Evidence used
Fictional contractor (invented)Sickness absence and leavers over 12 months; incident reports; a short anonymous staff survey; two group discussions of six
Groups especially at risk
Fictional contractor (invented)Projects, in the peak season from May to November
Arrangements
Fictional contractor (invented)The managing director owns the plan; progress is checked monthly with the safety representative; staff hear back at team briefings.
Next review
Fictional contractor (invented)December 2026, after the peak season, or sooner after a significant change
Demands
What we found, and who is affectedThree projects run at once with no agreed order. Evening work most weeks in peak season; every deadline falls in the same week in November. Who: Projects – a group especially at risk.
What we already doTwo extra agency staff in peak season
What more we will do: owner, by when, reviewA priorities meeting every Monday ending in one written list. Raise the November deadlines with clients before the next contracts. Owner: Projects manager; managing director. By: Meeting from May; clients by September. Review: Ask Projects staff in December; compare evening work with last year.
Control
What we found, and who is affectedNo significant finding. Crews say they have a say in how they do their work.
What we already doCrews plan the day at the morning meeting
What more we will do: owner, by when, reviewNone needed now. Review: At the next review.
Support
What we found, and who is affectedNew starters rate support from managers lowest. Crews at the second site rarely see their manager there. Who: First-year staff; crews at the second site.
What we already doFriday reviews in the Workshop, which staff value
What more we will do: owner, by when, reviewA buddy – a colleague, not a manager – for each new starter's first eight weeks. The operations manager at the second site every Tuesday. Owner: Office manager; operations manager. By: June. Review: Ask new starters at eight weeks; check visits monthly.
Relationships
What we found, and who is affectedThe Workshop reported four incidents in spring and heard nothing back. Some say people who raise problems at the morning meeting get labelled as difficult. Who: Workshop and Operations.
What we already doPolicy on unacceptable behaviour in the staff handbook
What more we will do: owner, by when, reviewA named reply to every incident report within five working days. Managers ask for problems at the start of each morning meeting. Owner: Workshop supervisor; managing director. By: May. Review: Monthly count of replies on time; team briefings in September.
Role
What we found, and who is affectedTwo project managers sometimes ask for the same crew in the same week, giving crews conflicting instructions. Who: Operations crews.
What we already doJob descriptions for every role
What more we will do: owner, by when, reviewCrews allocated once a week at the Monday meeting; the operations manager settles clashes. Owner: Operations manager. By: May. Review: Ask crew leaders in September whether clashes have stopped.
Change
What we found, and who is affectedNo significant finding. Staff valued having a say in choosing the Workshop's new tools.
What we already doChanges discussed at team briefings before they are decided
What more we will do: owner, by when, reviewInvolve staff the same way in the next change. Owner: Managing director. By: Ongoing. Review: At the next review.

Each action has an owner, a date and a check that it worked, as HSE's guidance on action plans asks, and the group especially at risk is named (reg 3(6)(b)). For keeping the actions moving, see the staff survey action plan.

Where the evidence comes from

The evidence comes from figures you already hold (absence, turnover, complaints, accidents and near misses), conversations with staff, group discussions and, where it is proportionate, a staff survey. HSE says a survey “is not an essential step” and that for smaller organisations it “would not be proportionate”, particularly where the same data can be gathered in other ways. How to do a stress risk assessment goes through each source; HSE's own survey is the Indicator Tool.

HSE's own template and example assessments

HSE's general risk assessment template, in Word and Open Document format, has a header for the company name, the assessor and the dates, and columns for the hazards, who might be harmed and how, what you already do, what further action you need, who carries it out, by when, and “Done”. HSE's stress page calls it an easy way to record your findings, and links three example stress assessments, each set out by the six areas:

«This example risk assessment is not a generic risk assessment that you can just put your company name on and adopt wholesale without any thought. This would not satisfy the law – and would not be effective in protecting people.»
HSE, Example risk assessment on work-related stress in a small business

HSE's Action plan and worked example has columns for the standard area, the “Desired state”, the “Current state”, “Practical solutions”, who takes the work forward, when, how staff will receive feedback, and whether the action is completed.

“Mental health risk assessment” or “stress risk assessment”?

HSE's guidance uses the term stress risk assessment, and describes its scope in these words:

«Employers have a legal duty to protect workers from stress at work by doing a risk assessment and acting on it. You should assess the risk of stress, and its impact on mental and physical ill-health, in the same way as you assess other work-related health and safety risks.»
HSE, Stress risk assessment

HSE also writes that “Stress is not an illness, but it can make you ill”, and that “You may need to develop individual action plans for workers suffering from stress.” How to do that is covered in individual stress risk assessments.

Keeping the record: who sees it, when to review it, and inspectors

Employees must be given comprehensible and relevant information on the risks the assessment identifies and on the preventive and protective measures (MHSWR 1999 reg 10; the same in Northern Ireland). The regulation speaks of information rather than of the record itself; HSE's example employers simply emailed the finished assessment to all staff. Union-appointed safety representatives may, with reasonable notice, inspect and copy relevant documents the employer must keep, except health records of identifiable individuals (SRSC 1977 reg 7(1)) – see health and safety representatives.

The law sets no fixed interval for reviewing it. You must review the assessment if there is reason to suspect it is no longer valid, or there has been a significant change in the matters it relates to, and make the changes that follow (MHSWR 1999 reg 3(3)). HSE's guidance says to “Review the risk assessment regularly and particularly after significant change”, and its example employers chose every year, or straight away after a major change – practice, not a legal deadline.

If an inspector asks, this record is what you produce. HSE's checklist for stress assessments explains why it pays to document the whole process:

«Documenting the process you have followed provides an audit trail to help you demonstrate to the relevant inspection authorities that what you have done represents a suitable and sufficient risk assessment.»
HSE, Is my risk assessment approach suitable and sufficient?

And from HSE's general guidance on risk assessment: “Do not rely purely on paperwork as your main priority should be to control the risks in practice.”

Sources

This is general information, not legal advice. We checked what the law says against legislation.gov.uk and the guidance of HSE, HSENI, Acas and the Information Commission (ICO) in October 2026.